I closed on the house yesterday and began to move things in today. There are a few items that remain to be finished in the house, but it is almost done!
Friday, February 4, 2011
Wednesday, February 2, 2011
Closing...
Only a few more days to go. They installed the crown moulding on the cabinets and installed the shower door.
Parts didn't arrive in time, so they built a temporary railing to pass inspection.
We had quite a bit of snow last night. It took all day for them to clear the street.
They cleared a small path and left a huge pile.
Monday, January 31, 2011
Sunday, January 30, 2011
Wrapping things up
Work continued at the house this weekend. I didn't have my usual camera with me when I stopped, but I was able to grab a few pictures with my phone.
Levers were being installed on the doors.
The deck was completed.
Friday, January 28, 2011
The final push continues
Today was a very busy day at the house. The plumbers installed the finish plumbing, the electricians continued installing lighting, the carpeting was finished, the garage door and gutters were installed and the appliances were delivered.
Garage doors, gutters and exterior lighting
Kitchen appliances and lighting
Hallway bathroom
Master bathroom