Friday, December 31, 2010

Hardwood Flooring

Since yesterday afternoon, they have made great progress at laying the hardwood flooring.





Happy New Year to everyone!

Thursday, December 30, 2010

Catching Up

It has been a busy week and a half for me as well as at the house.  Over the past week and a half, they finished taping the drywall, textured the walls and ceiling, painted and prepped to install the hardwood flooring.


Ceiling texturing:




Wall texturing:




Master bedroom paint color:

Spare bedrooms paint color:

 Bathrooms paint color:

Living room paint color:


 The hardwood flooring:

Sunday, December 19, 2010

Drywall Taping

Over the past few days they have been working on taping the drywall.




They also built the stairs on the deck.

Wednesday, December 15, 2010

Work continues...

Today they built the half wall for the breakfast bar and got the heat turned on in the house.


Tuesday, December 14, 2010

Work Continues

Over the past few days they finished hanging the drywall and began building the deck.





Looking into the master bathroom:



Inside the garage:




The deck: